The Calendar in Planner will allow Users to select a Specific Calendar for each Plan Board. The Calendar can be accessed by using the Navigation path Planner > Calendar.


 


The Calendar mode options are as follows 

  •  File 

 


FILE OPTIONS

Import local Gantter file...

Choose a Gantter File from your Local Drive and Import into Planner.

Import from MS Project...

MS Project files (.MPP) and files in MS Project XML format can be imported.

Import from P6 (XER)...

Files of (.XER) can be imported.

Import Calendars...

Choose a .gantter file from your Local Drive and Import into Planner.

Properties

Manage the following Schedule Properties - (General, Duration, Regional, Time Defaults, Resources, Notes, Links, Risks)

Export to local Gantter file...

Export your View as a (.gantter) file.

Export to MS Project (XML)... 

Export your View as a .XML file.

Export to P6 (XER)...

You have the option to - Export Roll Up Tasks Only, Export Rollup and Summary Tasks or Export All Task

Export to CSV (download)...

Export your View as a .CSV file.

Publish to Procore

The following Procore Publishing options are available - (Procore Connector Settings, Publish Now, Open Procore).

Export milestones to iCalendar(Download)...

Export your Milestones as a .ICS file.

Export milestones to web Calendar...

 Copy the Smartapp beta URL and use your web calendar's 'Add by URL" feature to add a new calendar with all the milestones for the schedule.

  • Edit

 


EDIT OPTIONS

Undo

Undo Edits CTRL-Z

Redo

Redo Edits CTRL-Y

Cut

Cut Text CTRL-X

Copy

Copy Text CTRL-C

Paste

Paste Text CTRL-V


  • View

 


VIEW

Reset View to Default

Selecting this resets the View to Default.

Fullscreen 

Selecting this sets the View to Fullscreen.

Sidebar

Unchecking this option hides the 5 Sidebar Mode Options.

Sidebar Modes

Click to Select a Sidebar Mode: Board, Schedule, Risks, Resources, Calendars

Show relevant risks

Click to only show Risks that are still relevant.

Show addressed risks

Click to show Risks that have already been addressed.

Show happened risks

Click to show Risks that have already happened.

Response Column

Show or Hide the Response Column.

Cause Columns

Show or Hide the Cause Column.

Probability Columns

Show or Hide the Probability Column.

Severity Columns

Show or Hide the Severity Column.

Priority Column

Show or Hide the Priority Column.

Actual Response Column

Show or Hide the Actual Response Column.


  • Action

 


ACTIONS OPTIONS

Insert Above

Insert a Task Above the Selected Task. 

Insert Below

Insert a Task Below the Selected Task. 

Delete

Delete the Selected Task.

Properties

View Task Board Properties.


  • Dispatch


DISPATCH OPTIONS

Dispatch Settings

Set Auto Dispatching to None, Hourly, Daily or Weekly. 


  • Baselines

BASELINES OPTIONS

Manage baselines

Add and Manage Baselines

None

Click to Select and Show a Baseline.


  • Widgets


WIDGETS OPTIONS

Constraints & Issues

Manage Constraints & Issues in the Constraints & Widgets Issues.




Last Updated: Dec-10-23