The Budget Manager has a calculator button that allows you to calculate the budget by entering unit measure, Unit quantity and unit cost.

  • To enter the original budget values you can use the calculator button as shown below.

  • Click on the calculator click on the button and fill in the below fields
  • Unit of Measure - Unit of Measure is based on the 'Cost Type' selected, it can either point to 'Unit of Measure - Time' or 'Unit of Measure - Quantity' list. 
  • Unit Quantity -  The standard unit quantity value.
  • Unit Cost - The unit  cost value.

 

  • Post entering these values clicks on the calculate button. The product of  'Unit Quantity' and 'Unit Cost' is populated in the 'Original Budget' field.