The video below will guide you on how to add predecessors to your tags and manage positive and negative lag:
Overview
This feature allows users to associate predecessors to tags and manage positive and negative lags, impacting task scheduling and dependencies.
Key Features
Associate Predecessor Tasks:
- Link tasks as predecessors and display their details in the Predecessor tab.
- Tasks can be from any board or CPM (Critical Path Method).
Manage Positive and Negative Lag:
- Positive lag is added when a tag is moved to the right.
- Negative lag is added when a tag is moved to the left.
Associate Rollup to Work Tag:
- Link a rollup to a work tag, displayed with a yellow "R" badge.
Extend Board End Date:
- Automatically extend the board's end date if the new lag pushes the task beyond the board's end date.
How to Use
Associating a Task as a Predecessor
Open Tag Properties:
- Click on the tag to open its properties page.
- Navigate to the "Predecessor" tab.
Add a Predecessor:
- Click on the "Task Name" field to open the dropdown.
- Select a task from the list to set it as a predecessor.
- Click "Save" to apply.
Visual Indicators:
- A yellow "P" badge appears on the tag, indicating zero lag.
- Hover over the badge to view predecessor details.
Managing Lag
Positive Lag:
- Move the tag to the right to add positive lag.
- The "P" badge changes to green.
- The lag value updates in the Predecessor tab.
Negative Lag:
- Move the tag to the left to add negative lag.
- The "P" badge changes to red.
- The lag value updates in the Predecessor tab.
Associating a Rollup
Link Rollup to Work Tag:
- During tag creation, associate a rollup in the "Scheduling Rollup Items" field.
- A yellow "R" badge appears on the tag.
Manage Rollup Movement:
- Moving a rollup also moves associated work tags by the same amount.
- The lag remains unchanged.
Extending Board End Date
- Automatic Extension:
- If the lag pushes the task beyond the board’s end date, a popup will appear.
- Confirm to extend the board's end date accordingly.
Important Notes
- Multiple Predecessors: More than one predecessor can be added to a tag.
- Manual Lag Adjustment: Users can manually adjust lag values in the Predecessor tab.
- UI Changes: Ensure any UI changes are approved by the User Interface team.
Last Updated: Dec-15-24