This guide explains the process of manually updating Vendor and Client Contracts after a Change Event has been approved. It covers the necessary steps, from unlocking the contract to making adjustments and reposting.
Manual Update of Vendor Contracts (GC Login)
Once the client approves a Change Event, new budget items are automatically created for the Work Items involved
The approved Change Event introduces additional Work Items in the Vendor Contracts which are marked with a 'C' icon, indicating that the Schedule of Values (SOV) needs to be adjusted
The contract's status changes from 'Active' to 'Active - Need SOV Update'
The contract creator (GC) clicks 'Unlock Contract' to unlock the vendor contract
Options for Unlocked Contracts:
Cancel: Reverts the contract to its previous state without any changes
Lock & Post Contract: Allows the GC to lock and post vendor contract directly
Route For Approval: Routes the vendor contract for approval after necessary changes have been made
To update the SOV, GC clicks 'Unlock Billing Schedule' and a notification appears indicating that the Billing Schedule can be modified
For the updated Contract Amount and new Change Event Amount, the Billing Schedule needs to be adjusted to match the revised values
After making the necessary adjustments, the changes are auto-saved in the Billing Schedule
If 'Payment Status' is 'Paid,' the 'Payout Amount' remains locked. The system auto-adjusts only the percentage payouts for paid items with the change event amount added to the contract amount.
Other statuses show a blank 'Payout Amount' which needs to be filled in by the GC
An event is logged in the 'Change Events' tab
The contract status changes from 'Active Unlocked - Need SOV Update' to 'Awaiting Acceptance'
A notification is sent to the Subcontractor and the Sub must log in to accept the contract for it to become 'Active'
Manual Update of Client Contracts (GC Login)
After client approval of a Change Event, new Budget Items are automatically created for the affected Work Items
Existing Client Contracts need to be manually updated and the work Items requiring updates are indicated by a 'C' icon, signaling the need to adjust the Schedule of Values (SOV)
The contract's status changes from 'Active' to 'Active - Need SOV Update'
The contract creator (GC) must unlock the contract to make modifications. Clicking 'Unlock Contract' initiates this process
Options for Unlocked Contracts:
Cancel: Reverts the contract to its previous state without any changes
Lock & Post Contract: Allows the GC to lock and post client contract directly
Route For Approval: Routes the client contract for approval after necessary changes have been made
To update the SOV, click 'Unlock Billing Schedule' and a notification appears indicating that the Billing Schedule can be modified
After making the necessary adjustments, the changes are auto-saved in the Billing Schedule
If 'Payment Status' is 'Paid,' the 'Payout Amount' remains locked. The system auto-adjusts only the percentage payouts for paid items with the change event amount added to the contract amount.
Other statuses show a blank 'Payout Amount' which needs to be filled in by the GC
An event is logged in the 'Change Events' tab
The contract status changes from 'Active Unlocked - Need SOV Update' to 'Awaiting Acceptance'
A notification is sent to the Sub Contractor, and an event is logged in the 'Change Events' tab and the Client must log in to accept the contract for it to become 'Active.'
Last Updated: Dec-15-24